BIM Coordinator Program (INT) April 22, 2024
Find the next step in your career as a Graphisoft Certified BIM Coordinator!
Collaboration with other software
About model and data exchange with 3rd party solutions: Revit, Solibri, dRofus, Bluebeam, structural analysis solutions, and IFC, BCF and DXF/DWG-based exchange, etc.

How to multiply the exposed surface area with a factor in Surface Schedule

Anonymous
Not applicable
Hello
I am working with Tiles estimation. I got the Tiles area using the field name ( exposed surface area) . Now I need to multiply this area with some factors . (such as labor factor/ wastage factor / ...)
How can I do this . Can anyone please help me ? My schedule is attached here
1 REPLY 1
Barry Kelly
Moderator
You can't do any calculations in the interactive schedules, other than simple summation of columns.

What you will need to look into is expressions in properties (search these forums and Archicad help).
You can associate a property to your elements )Walls and slabs).
This property can contain an expression (formula) that can calculate the figure you are after - i.e. multiply the surface area by the labour/waste factor.
You may need more than one property which is fine, and these properties can be used in expressions of other properties.
You can then schedule the resulting property rather than the surface area.


Barry.
One of the forum moderators.
Versions 6.5 to 27
Dell XPS- i7-6700 @ 3.4Ghz, 16GB ram, GeForce GTX 960 (2GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11
Learn and get certified!