Missing zone on Door schedule

Anonymous
Not applicable
I figured it out. Whenever the height between floors is less than 3'-6", the zone does not show up.
2 REPLIES 2
Anonymous
Not applicable
While running a door schedule, the schedule picked up the doors from a 3rd story but not the zones. Of note, the 4th story was 2'-5" above the 3rd. When the 4th story was eliminated, the zones were picked up by the schedule. Is there a way to remedy this and not eliminate the 4th story?
Durval
Enthusiast
Hi giuseppe,

I'm having a very similar issue:

http://archicad-talk.graphisoft.com/viewtopic.php?t=41544

Did you find an answer?
--- www.dtabach.com.br ---
AC 24 BR – MacBook Pro 2,9 GHz Intel Core i7 16GB RAM Mac OS 10.14