Just trying to work out the best way to do this.

I have a room where a wall is to be demolished, the room reduced in size and then a larger room created adjacent as part of new-build extension (hence partly in the original existing zone).

Does this mean that the whole of the original zone should be in 'demolition' a new zone created for the reduced existing room and the enlarged adjacent zone ?

Or is there a way of splitting zones into existing and demo components ?