Phasing workflow

bouhmidage
Advisor
Hi,
The actual phasing solution is the Renovation filter, But, i have a project with
* 5 phases,
* some special " interventions" like removing claddings, adding some skins to walls, changing door panels only,

what is the best workflow for such a situation ? the renovatio filter is limiting the choices here
AMD Ryzen 9 3900X, 32 GB RAM, RTX 3080 10 GB
Archicad 25
Windows 10 professional
https://www.behance.net/Nuance-Architects
4 REPLIES 4
Laszlo Nagy
Community Admin
Community Admin
You might want to experiment with the "Show on Renovation Filter" field of elements.
You can create Renovation Filters, and then you can set certain elements to show only on those specific Filters, instead of being based on the "All Relevant Filter" setting of the field. (This way you may or may not achieve your goal, I would have to see the exact scenario.)
Loving Archicad since 1995 - Find Archicad Tips at x.com/laszlonagy
AMD Ryzen9 5900X CPU, 64 GB RAM 3600 MHz, Nvidia GTX 1060 6GB, 500 GB NVMe SSD
2x28" (2560x1440), Windows 10 PRO ENG, Ac20-Ac27
bouhmidage
Advisor
here is some screenshots
AMD Ryzen 9 3900X, 32 GB RAM, RTX 3080 10 GB
Archicad 25
Windows 10 professional
https://www.behance.net/Nuance-Architects
bouhmidage
Advisor
I was thinking about solutions and here what i find so far :
* i can't change a component unless i replace the entire wall or door.
* to show phasing , i found three solutions
1 - graphic override : create a propretie with phase numbers : 1, 2, 3, 4, ... n phase, then override each phase according to it's propretie value, this can be done the show all phases with different colors,
2 - layer combination : each phase has it's own layer, or a bunch of layers to keep all organized ( walls, slabs, columns of phase 1, the same for phase 2 etc)
visibility can be controlled via layer combinations
3 - linked modules : each phase have to be modeled in a seperate file, then, the are linked to a common file, and the rest is just layer combination work.
AMD Ryzen 9 3900X, 32 GB RAM, RTX 3080 10 GB
Archicad 25
Windows 10 professional
https://www.behance.net/Nuance-Architects
Erwin Edel
Rockstar
We use custom renovation filters a fair bit for showing elements on specific views only. This does limit you to hiding / showing those specific 'phases' only though. You can't pin things to 'phase 1' and other things to 'phase 2' and then show both of them at the same time.

Going of the cladding you mentioned. You could show or hide a layer for that.

You could 'demolish' your door and have two new doors, where you pin them to a specific filter. The first door would be an emtpy frame (if you need this) and the second door would be the frame with the leaf.

I quite often have renovations where we only change part of a door or window. I still demolish the old door with frame and place a complete new one and just annotate on my layouts that only the leaf should be replaced. Shortcomings in the software, but I'm not going to spend hours on something that a quick text explanation will fix.

For colour coding, the easiest thing to use is Graphic Overrides indeed. You could add the phase numbers to element ID or you could make a custom property that you set for each element.