Hello,

 

I'm trying to understand if it's possible (and somehow accurate) to schedule some objects volume. Typically joinery items (I'm using Ci Cabinets & Wardrobe 23), and locker 23. 
I need to schedule these volumes to make sure we match the min. requirements. 

Here is my schedule for the external storage, I'm using Locker 23. 

VincentG__0-1632485497771.png


The locker is 1700x875Dx2550H, should be ~3.8m3 brut (without counting the "frame"). I've tested every available volume but the only one working is net: 0.29 with the sum of all of them 4.35m3 

VincentG__1-1632485714105.png

 

Obviously not right. The same happens when I try to do the same for internal storage (wardrobe 23 & Ci cabinet). 

Am I missing something? Or is it just that objects can't be scheduled unless GDLed specifically? 
I could use zones or columns on a special layer as I used to do but I thought why not trying to directly schedule the object to avoid extra maintenance,

1 ACCEPTED SOLUTION

Solution
Rajesh Patil
Advocate

Try to use "Classification & Properties" and define a New Property as shown below

Step 1Step 1Step 2Step 2Step 3Step 3Step 4Step 4

Rajesh Patil
AC 09-25 | INT | WIN10 64
Dell Inspiron 7591, Core i9, 9880H 2.30GHz, 16.0GB, NVidia GeForce GTX1650, 4.0GB, SSD Internal 500GB, Dell SSD External 250GB

View solution in original post