Doors schedule - zone excluding problem

Anonymous
Not applicable
Hi,

I've created a door schedule to list all interior doors of a floor plan by a certain set of zones. It excludes other subzones through layer filtering.

This works fine for the project I created it in, but it doesn't work by importing it into another project. Creating the same schedule from scratch in this project doesn't work either. The door schedule doesn't want to exclude the zones I've put on a layer that is excluded through it's criteria and lists all zones drawn in the project...

Any suggestions?
2 REPLIES 2
Anonymous
Not applicable
I can imagine why the import might not work, but not when it's rewritten
from scratch.
vfrontiers
Enthusiast
---here's my one post for the year!---

I am assuming you've got OVERALL zones and then SUBZONES drawn on top of each other, each on a separate layer, yes?

It has always been my experience that it is NOT possible to link any object to more than one zone. I am not clear how it picks which zone to attach itself to, but it can only have one.

I don't know if this is different in 13 (stuck in 12 at the moment)....
Duane

Visual Frontiers

AC25 :|: AC26 :|: AC27
:|: Enscape3.4:|:TwinMotion

DellXPS 4.7ghz i7:|: 8gb GPU 1070ti / Alienware M18 Laptop