Mid Level Doors in Schedule

vfrontiers
Enthusiast
So I've been using this door schedule ever since interactive schedules came out...

Now I have a house with a SPLIT LEVEL where I'm showing all the mid level walls on the UPPER story.

My schedule, however, has determined for me, that these doors should show up with the FIRST LEVEL doors...

I have forced the affiliation of the walls to the 2nd Level, but they keep showing on the 1st Level's schedule...

Any ideas greatly appreciated...
Duane

Visual Frontiers

AC25 :|: AC26 :|: AC27
:|: Enscape3.4:|:TwinMotion

DellXPS 4.7ghz i7:|: 8gb GPU 1070ti / Alienware M18 Laptop
1 REPLY 1
Barry Kelly
Moderator
You could duplicate your schedule and then add a criteria to each to filter the height from project zero.
One for the low wall and one for the higher level.
Barry.
One of the forum moderators.
Versions 6.5 to 27
Dell XPS- i7-6700 @ 3.4Ghz, 16GB ram, GeForce GTX 960 (2GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11
Learn and get certified!