what operator error is it this time ?
see attached graphic

Michael |:-)
AC 4.5 - 19 Build 3003 Full USA
Mac OSX 10.10
AC 4.5 - 19 Build 3003 Full USA
Mac OSX 10.10
Labels:
- Labels:
-
Data management
3 REPLIES 3

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎2010-12-04 02:32 PM
‎2010-12-04
02:32 PM
Michael:
Those look like parameters that are used with the MEP add-on, so you may not be able to use them if you don't have the add-on, or are using a dongle that does not have a MEP license. It is also possible that the objects are locked or on a locked layer, but the Interactive Schedule would let you know (warning at the top of the schedule dialog box).
David
Those look like parameters that are used with the MEP add-on, so you may not be able to use them if you don't have the add-on, or are using a dongle that does not have a MEP license. It is also possible that the objects are locked or on a locked layer, but the Interactive Schedule would let you know (warning at the top of the schedule dialog box).
David
David Maudlin / Architect
www.davidmaudlin.com
Digital Architecture
AC28 USA • Mac mini M4 Pro OSX15 | 64 gb ram • MacBook Pro M3 Pro | 36 gb ram OSX14
www.davidmaudlin.com
Digital Architecture
AC28 USA • Mac mini M4 Pro OSX15 | 64 gb ram • MacBook Pro M3 Pro | 36 gb ram OSX14
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎2010-12-05 01:46 AM
‎2010-12-05
01:46 AM
David wrote:David ........
Michael:
Those look like parameters that are used with the MEP add-on, so you may not be able to use them if you don't have the add-on, or are using a dongle that does not have a MEP license. It is also possible that the objects are locked or on a locked layer, but the Interactive Schedule would let you know (warning at the top of the schedule dialog box).
David
Nope, all layers and objects unlocked......I will work around this schedule and use a customized Plumbing Schedule instead....thank you for your insights as this will save many hours of trying to figure it out....Perhaps GS should withdraw this from the standard pull downs so as not to confuse the un-expecting users ? ............Thank you !
Michael

Michael |:-)
AC 4.5 - 19 Build 3003 Full USA
Mac OSX 10.10
AC 4.5 - 19 Build 3003 Full USA
Mac OSX 10.10

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎2010-12-05 02:42 PM
‎2010-12-05
02:42 PM
Michael wrote:The "Plumbing Fitting Schedule" does not have the MEP parameters, the "Plumbing Fixture Schedule(s)" do, so better naming would help. My guess is that most users are going to modify these sorts of schedules anyway.
....Perhaps GS should withdraw this from the standard pull downs so as not to confuse the un-expecting users ?
Glad to help.
David
David Maudlin / Architect
www.davidmaudlin.com
Digital Architecture
AC28 USA • Mac mini M4 Pro OSX15 | 64 gb ram • MacBook Pro M3 Pro | 36 gb ram OSX14
www.davidmaudlin.com