Hi every one i copied doors and windows from other projects of mine so i am intending to copy them always in every project if i made them in floor say -2 under ground floor can i exclude it from calculated inside schedule please tell me how and thanks
1 REPLY 1
vistasp
Advisor
Hi Ahmed,

It might look a little different in v14/15 but essentially, you have to add a criterion that eliminates all doors/windows on the storey -2.