Please provide the ability to schedule elements that are placed in viewpoints other than a story (i.e. schedule fills that are on a worksheet or a defined set of elevations/sections to would allow for 2D take-off diagrams which do not clutter the primary working area of the model).


Including more schedule options for fills, not just area and attribute based info.

2 Comments
Barry Kelly
Moderator

The problem with scheduling elements that are not in the actual model is that you will be more inclined to repeat the same thing in different views.

So the same element may get counted multiple times because you need to see it in each view.

Of course you can still add multiple elements in the model but that is just a QA issue.

 

Barry.

TaniavH
Enthusiast

this should be view based somehow - the scheme settings should allow you to isolate what's being scheduled on a by-view basis, not "let's schedule all the fills in the file" - nobody wants that...