Barry wrote:Thanks Barry for your information...
Property Objects are part of the old list schemes.
As far as I know the list schemes are being phased out in favour of the Interactive Schedules.
Or at least they are not being updated and new tools such as the stairs and railings are not being included.
This is going to be a big problem until we can start doing calculations in the interactive schedules.
Barry.
2017-11-15 11:45 PM
Barry wrote:In his actual form the schedule system is IMO an absolutely useless way to list materials.
Property Objects are part of the old list schemes.
As far as I know the list schemes are being phased out in favour of the Interactive Schedules.
Or at least they are not being updated and new tools such as the stairs and railings are not being included.
This is going to be a big problem until we can start doing calculations in the interactive schedules.