Equivalent Single Dwelling calculation in schedule?

Aloha,

Our jurisdiction is now requiring that we calculate and report the ESD (water usage) using this formula:

ESDs = [1.15(Baths)1.3 + Beds + 3] / 10

Is there a way to have a schedule do this calculation after inputing the number of bedrooms and bathrooms?

 

Operating system used: Mac Apple Silicon Ventura 13.5

1 Reply 1
Barry Kelly
Moderator

Schedules can not d any calculations other than simple summation of columns/rows.

 

Classification and Properties can be used though.

Look at Properties with expressions where you can create a property with this formula.

 

https://help.graphisoft.com/AC/29/INT/index.htm?rhcsh=1&rhnewwnd=0&rhmapid=#t=_AC29_Help%2F045_Prope...

 

There are also many posts here.

 

You would need a property for the number of beds, another for the number of baths and then a third to do the calculation.

You could than associate these to a zone for the apartment area where you can adjust the number of beds/baths for each zone and then get the resulting calculation.

 

You can then schedule the resulting property or even use it in a label you can add to each zone in plan.

 

Barry.

 

 

 

 

One of the forum moderators.
Versions 6.5 to 27
i7-10700 @ 2.9Ghz, 32GB ram, GeForce RTX 2060 (6GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11

Didn't find the answer?

Check other topics in this Forum

Back to Forum

Read the latest accepted solutions!

Accepted Solutions

Start a new conversation!