Team,

What is your view on this situation? Do any of you have experience in managing something similiar? what would you recommend?

In this new project we are working on, it is going to have the office bldg wrapping up beside and then over the parking garage. We’re spacing the floors on level 1-5 so that basically its 2 levels of garage per 1 level of building. Now for managing stories on this thing, do you know of any way around doing this? It's a 10 story building but the first 5 levels will incluse 2 levels of Parking for each floor.

Would it be best to seperate this in two files? and then hotlink them. Any help would be appreciated.
15 REPLIES 15
Rob
Graphisoft
Graphisoft
mate, I like your signature but you should expand it:

User since v 3.15 (!)... proudly using v 4.55!
::rk
Anonymous
Not applicable
hey - sorry if you were offended by anything I said. I don't think anything I've said warrants that. Though I actually use v10 at the moment. There are times I go back and use 7 though - as it can be more effective. But there's really no reason to act like an ass on a public forum. I
Anonymous
Not applicable
(I think the wink smiley indicates he may have been joking)
Rob
Graphisoft
Graphisoft
hey - sorry if you were offended by anything I said....But there's really no reason to act like an ass on a public forum.
chill out mate, do not make a drama out of it...
::rk
Djordje
Virtuoso
JWD wrote:
clearly there are MORE THAN TWO different solutions to the problem that would be satisfactory - and it would really depend on having a detailed look at the actual project, and the person working on it, the team, etc etc..
There are as many solutions as there are people ... that's called flexibility. As they say in the car ads, your mileage may vary or YMMV.

However, you should think about an upgrade if economically viable - and the two version upgrade usually is. 10 started a new generation of ArchiCAD, that is being built upon, so ... it is worth checking out at least.
Djordje



ArchiCAD since 4.55 ... 1995
HP Omen
Anonymous
Not applicable
I just am working on a similar project as described - garage with half levels and adjacent housing with the main levels at a level half above grade. It turned out to use the one file with the stories as Laura indicated - it makes for easier management of the module insertion and using a story naming convention that is easier to relate to keeps the mind working as the model. We will see if continuing with this set up works.

Lew Bishop
Jon Worden Architects
MBP 2.16 17" 2Gb