Hi,
Working with an industrial project where I have a large multi storey zone and doors from different stories open into this zone. When scheduling "To zone" for the doors only the doors which have the same home story reports the zone in the "To Zone" property. Is there a way to solve this other than dividing the multi storey zone into one zone per story (which gives incorrect total m2)? The screenshot is just and example. My project is 50000m2.
/Mats
Operating system used: Windows
Solved! Go to Solution.
a week ago
Unfortunately not.
Zones can be stretched across multiple floors by height, but they can not be multiple storey.
Barry.
a week ago
Unfortunately not.
Zones can be stretched across multiple floors by height, but they can not be multiple storey.
Barry.
a week ago
Thanks Barry,
Suepected that. Troublesome.
I'd be sooo happy to work with a small villa in Archicad...but that never happens.
/M