I'm truying to select windows on the plan to modifie them with the button on the top left corner. For some of my doors, the option is disable. What to do?

Tank you for your help.
1 ACCEPTED SOLUTION

Accepted Solutions
Solution
Barry Kelly
Moderator
Your plan is probably set to a different layer combination to the one set in the view that you opened the schedule with.

What I do is open the floor plan so you can see your doors.
Now open the schedule from the Project Map and not the View Map.
This will use the same setup as the plan and not those saved with the view in the View Map.

Those buttons should then be available for use.


Barry.
One of the forum moderators.
Versions 6.5 to 27
i7-10700 @ 2.9Ghz, 32GB ram, GeForce RTX 2060 (6GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11

View solution in original post

7 REPLIES 7
Anonymous
Not applicable
Have you checked if your Groups are set to on?
HTH
Solution
Barry Kelly
Moderator
Your plan is probably set to a different layer combination to the one set in the view that you opened the schedule with.

What I do is open the floor plan so you can see your doors.
Now open the schedule from the Project Map and not the View Map.
This will use the same setup as the plan and not those saved with the view in the View Map.

Those buttons should then be available for use.


Barry.
One of the forum moderators.
Versions 6.5 to 27
i7-10700 @ 2.9Ghz, 32GB ram, GeForce RTX 2060 (6GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11
Anonymous
Not applicable
Tank you Barry, it make sense. I will try it.
Anonymous
Not applicable
Look at my screenshot. I'm in the project map and stil the same.
Anonymous
Not applicable
Braza wrote:
Have you checked if your Groups are set to on?
HTH
Look at what it does every times I go to the door schedule. It aide stuff and put the slab pink.

It also change my layer setting to custom. Possibly he can not see the doors because they are hidden. Whatever from where I open the table, it's the same.
Anonymous
Not applicable
Finally I had to change "Custom" for "floor plans" in "Layer Combination" in the schedule.
Anonymous
Not applicable
I guess you haven't correctly understand the concepts of Project/View/Layout Map.
You can find help here: https://archicad-talk.graphisoft.com/viewtopic.php?f=13&t=68874#p306024
See if it can help.