Hello everbody,
1. Create a 'container' file and hotlink in the entire model, then move to the module to GC and export
- sorry, BUT this is NOT a workaround - that is the correct, practical workflow for this - it is the solution for this...
and as far as I know (and in my experiance) ARCHICAD has - I think since version 8.x and special method dealing with projects very far from origin (0,0) - "fast, symbolic description":
ALL - whatever - elements in a ARCHICAD-project (file/TW) in ALL views are surrounded by a rectangle - the corner "left/down" will be taken as the "new INTERNAL origin" for all elements, so relations between elements are the same, correct "vector-calculating" is the same as at the "original" origin --> there (should be) is no differenc to "situation near orig. origin"...
BUT , if you "forget" this special "situation" and someone creates a new level to do some drafting / lib-objects-creation / import ifc-file / ... , then you suddenly fall into deepest hell... the valley of tears... OMG - most of the time only a backup will save "you"...
...because "suddenly" ARCHICAD recreacte/alter the virtual, internal, surrounding rectangle (prism), which defines the temporally, internal, origin...
suddenly all the negative effects can happen which will happen when your project is situated at x= +357.245,00 m / y=+48.157,25 m ...
the solution developing the whole project "normal" at/near default 0,0 and "hotlinking" this PLN/TW into an other (second) project and there at the "real" world-coordinates (far away from default-0,0) is the correct and rational workFLOW and NOT workaround...
hope I could help solving your question
- you are welcome
best regards from vienna,
Klaus