3 weeks ago
Hello, I worked on a big house renovation project (project #1) and will now be be working on different elements of the house (project #2). Is there a way to convert all the ''planed status'' /existing conditions that were not demolished of project #1 into EXISTING to create the new base for project #2 so I can now work on existing/demo/new construction elements.
Thanks!
Operating system used: Windows 10
Solved! Go to Solution.
3 weeks ago
Check the "Reset Renewal Status" option.
It may help.
3 weeks ago
3 weeks ago
Amazing, thanks!