hoggs wrote:I guess you can see the value of establishing the BIM implementation plan up front so these problems can be kept to a minimum. Project origin and rotation should be established up front and strictly adhered to by all participants.
Thank you for your answer, that helped a lot.
I'm working as a BIM coordinator for a large contractor and we are trying to utilize the benefits of BIM.
We're using Solibri Model Checker to do collision checking and therefor the IFC format for exchanging files.
In this project the structural engineer rotated his model according to the projects north, but we agreed on not rotating the models for simplicity.
The structural engineer say it's a lot of work to rotate this model right, so therefor I'm trying to enter the right rotation in Solibri.
I guess it will work with this accuracy, but it is not ideal and I probably have to read through some errors caused by this.