Jere wrote:I have the lower stretch line @ the bottom of the footing. If I move it to the top, will this fix that?
Only fills are used in a complex profile. Lines are only used as a drafting aid. If you want your anchor bolts and rebar to be modelled, they have to be drawn. Personally, I'd add the rebar on a detail drawing.
To get the footing and wall to be separate, they need to be different fills. If you want them to be the same fill, just make a copy of the new fill under a different name.
Example:
wall: concrete fill1
footing: concrete fill2
Do you have the lower stretch line at the top or bottom of the footing?
2009-07-20 05:54 PM
2009-07-20 05:55 PM
2009-07-21 04:54 AM
2009-07-21 05:39 AM
2009-07-21 02:25 PM
lec1212 wrote:I have talked it over in the office and we are not going to show any rebar in the foundation, we will just add it as we detail as you have suggested. It is a large pain in the you know what to set that up with all the rebar...
Steve
Along with mud sill you could also make your J bolts also show up in C.P. made with different fill than mud sill or fnd fill.
Just don't use rounded edges for lower poly count as Erich implies.