Window #s and the interactive schedule

Anonymous
Not applicable
I have been setting up our window and door schedule using the interactive schedule. We use the ID as our window or door number and use this to order the schedule. The only problem is for windows or doors that are labeled 1-9. In the past I have labeled these windows 01 - 09 to assure the schedule orders correctly, but was curious if there is a means to use 1-9 and have them all show up in the schedule in front of 10. Thanks in advance for any ideas.
1 REPLY 1
Link
Graphisoft Partner
Graphisoft Partner
You could cheat and put a space before the 1-9's!

Cheers,
Link.