When I use AC12 and and interactive schedules the result is partially right. In the attached picture 3 columns are wrong : SHOB, d and S'x0,95. When I collect the data and use MSXLS to calculate the sums, the result is totally correct. Same with any calculator.
How can I set AC12 to get all sums correct ? Is it possible ? Are there specific settings to push AC12 to display correctly this quantities collected from zones within interactive schedules ?
Labels:
- Labels:
-
Data management
2 REPLIES 2

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎2009-04-30 01:44 PM
‎2009-04-30
01:44 PM
Til:
This could be due to a rounding error, can you display greater precision for the AC schedules? Also, for column S'x0,95, my calculator shows that 84.42 x 8 = 675.36, so the AC schedule seems correct, and the XLS is wrong.
HTH
David
This could be due to a rounding error, can you display greater precision for the AC schedules? Also, for column S'x0,95, my calculator shows that 84.42 x 8 = 675.36, so the AC schedule seems correct, and the XLS is wrong.
HTH
David
David Maudlin / Architect
www.davidmaudlin.com
Digital Architecture
AC28 USA • Mac mini M4 Pro OSX15 | 64 gb ram • MacBook Pro M3 Pro | 36 gb ram OSX14
www.davidmaudlin.com
Digital Architecture
AC28 USA • Mac mini M4 Pro OSX15 | 64 gb ram • MacBook Pro M3 Pro | 36 gb ram OSX14
Anonymous
Not applicable
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎2009-04-30 03:04 PM
‎2009-04-30
03:04 PM
David
Warning there is a trap :
IS are not linked to the "Options/Project Preferences/Dimensions" settings,
IS are linked to the "Options/Project Preferences/Calculations Units" settings
The result will show correctly only if I turn of decimals (as shown on the images attached)
When ever a decimal is displayed one of the columns will generate a calculation error.

Thanx a lot David
David wrote:yes understood, and found it.
This could be due to a rounding error, can you display greater precision for the AC schedules?
Warning there is a trap :
IS are not linked to the "Options/Project Preferences/Dimensions" settings,
IS are linked to the "Options/Project Preferences/Calculations Units" settings
The result will show correctly only if I turn of decimals (as shown on the images attached)
When ever a decimal is displayed one of the columns will generate a calculation error.
David wrote:Waow you are right, I should maybe send another post to MS
Also, for column S'x0,95, my calculator shows that 84.42 x 8 = 675.36, so the AC schedule seems correct, and the XLS is wrong.