How can I copy a schedule's format between projects

I have several schedules that were successfully created on one project and now I would like to update my new template. Is there a cut and paste or export-import?
Todd Oeftger
AC27 Mac MacBook Pro 15", 2019, 2.3 GHz i9, 32GB, Radeon Pro 560X 4GB, 500GB SSD, 32" Samsung Display (2560x1440)
1 Reply 1
Steve Jepson
Virtuoso
Import -Export


You can import multiple Schedules at one time also. No risk of duplication because the program will automatically add a number to the name of the Schedule if it is a duplicate. If you import a Schedule from a newer version of the program to an older version a warning will pop up to let you know that you may need to check the schedule for fields that may not be available in the older version.

ArchiCAD 25 7000 USA - Windows 10 Pro 64x - Dell 7720 64 GB 2400MHz ECC - Xeon E3 1535M v6 4.20GHz - (2) 1TB M.2 PCIe Class 50 SSD's - 17.3" UHD IPS (3840x2160) - Nvidia Quadro P5000 16GB GDDR5 - Maxwell Studio/Render 5.2.1.49- Multilight 2 - Adobe Acrobat Pro - ArchiCAD 6 -25

Still looking?

Browse more topics

Back to forum

See latest solutions

Accepted solutions

Start a new discussion!