Thanks for your response Laszlo,
Your question contained the answer: I didn't appreciate the difference between an element and a component schedule, but that difference is the key. Once I made an element schedule rather than a component schedule, "Quantity" started counting the individual beams, rather than the components that created the beams. 
Thank you!
					
				
			
			
				