We have a 10+ level project, which is unusual in our office, and our doors labeled 10xx are being scheduled among doors labeled 1xx. For example, the doors would be sorted by order of door ID 1028, 1029, 103, 1030, 1031. The door ID is based off the NCS marker which reads the zone the door is swinging to or from.
I understand a solution is placing the zero before the 3-digit numbers such as 0103, 0104, etc. but since the door ID is being read from the zone/room numbers, we'd prefer NOT to place the zero before the 3-digit numbers.
Is there by any chance I'm missing a schedule setting that would sort the four digit 10xx door IDs at the end of the schedule? Or a reasonable work-around? This is being done in AC14. Thanks!