Hi ..I need really help about wall and column plan or section :
As you know we have problems with the wall finishing attaching to a slab core in section while we using Wall Composite .... this problem could be solved by using Wall complex profile ... but when I used this solution, i got another problem... in this case, my columns couldn't warped by wall finishing ... actually it seems that column just work with composite wall not with complex profile wall !
So what can I do to have both good finishing connection of wall and slab in section .. and column warping in plan ?
here is the picture of my problem !
I can solve this by using composite structure while using 2 slab one of them should be just Core ... and put 2 new slab composite contains finishing part on both side of wall !!! But it's really kinda not good idea !!