pallsopp42 wrote:Don't see your screenshots. You can attach one per post, and there is a size limitation of 256kb as I recall.. so you'll have to lower the jpeg quality, use gif, etc. Or provide links to an external photo hosting site.
Below are some screen shots of what I'm seeing
2013-06-30 03:37 PM
2013-07-01 04:01 PM
2013-07-01 04:03 PM
2013-07-02 04:02 AM
pallsopp42 wrote:I don't know much about Ecodesigner but there is nothing in this operation profile that tells it that it is only for 9 hours per day.
Karl:
per my previous note, I have - hopefully - attached two screen shots that show the large discrepancy between a 2-day-per-week; 9-hour day operational profile for the building's energy recovery ventilation system and the Operational profile of the building (occupancy, temperature ranges etc.).