How to Set Story 0 as the Reference Level for Dimensions

mrsneuna
Booster

I would like to make Story 0 (Lobby) the reference level for my dimension levels, so that the Lobby level becomes +0.05 instead of +1.05. How can I adjust the reference level so that the elevation dimension starts from Story 0?

mrsneuna_0-1762937862939.png

 

Operating system used: Windows 10

1 ACCEPTED SOLUTION

Accepted Solutions
Solution
Erwin Edel
Rockstar

You can set a seperate custom reference level in Options > Project Preferences > Reference Levels. Offset that by the 1 meter needed and you can set your level dimensions to use the custom level instead in the Text Content either as single value or as a custom text.

Erwin Edel, Project Lead, Leloup Architecten
www.leloup.nl

ArchiCAD 9-29NED FULL
Windows 11 Pro for Workstations
Adobe Design Premium CS5

View solution in original post

5 REPLIES 5
Solution
Erwin Edel
Rockstar

You can set a seperate custom reference level in Options > Project Preferences > Reference Levels. Offset that by the 1 meter needed and you can set your level dimensions to use the custom level instead in the Text Content either as single value or as a custom text.

Erwin Edel, Project Lead, Leloup Architecten
www.leloup.nl

ArchiCAD 9-29NED FULL
Windows 11 Pro for Workstations
Adobe Design Premium CS5
Barry Kelly
Moderator

Or set storey zero to 0 instead of 1000,

But that is probably a bit late now as you would have to adjust all of the other storeys and then move any annotation you have added to sections and elevations.

 

Probably best to use a reference level as Erwin suggests.

 

Barry.

One of the forum moderators.
Versions 6.5 to 27
i7-10700 @ 2.9Ghz, 32GB ram, GeForce RTX 2060 (6GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11
Erwin Edel
Rockstar

I think project zero (and story 0) is being used as some sort of real world level dimension and it's probably a pain in the behind to change it now.

 

We use a reference level for the real world level dimension, since this is generally a flexible level throughout the span of a project.

Erwin Edel, Project Lead, Leloup Architecten
www.leloup.nl

ArchiCAD 9-29NED FULL
Windows 11 Pro for Workstations
Adobe Design Premium CS5

I have another problem

When I move the slab down by 5 cm, the level dimension doesn’t update automatically it still shows +0.00 instead of -0.05. How can I make the level dimension automatically update to reflect the new slab elevation?

You did use the 'Level Dimension Tool'?

If so make sure it is not set as 'Static' or custom text.

It will associate to and adjust with the slab.

 

Barry.

 

One of the forum moderators.
Versions 6.5 to 27
i7-10700 @ 2.9Ghz, 32GB ram, GeForce RTX 2060 (6GB), Windows 10
Lenovo Thinkpad - i7-1270P 2.20 GHz, 32GB RAM, Nvidia T550, Windows 11

Setup info provided by author