2024-11-27 02:21 PM
Hi.
I have a slab that above it has 2 existing steps that im trying to model.
I would think the proper worfflow would be:
1. have base slab;
2. create 2 slabs above with just cement filling+ceramic finish and stack them on each other;
3. make sure the cement filling layer of the base slab is touching the cement filling of the secondary slab that sits on the original one, so they connect and i eliminate the ceramic layer in between.
But even though the intersection priority of the cement filling is higher than the ceramic tile, when i do the baove operation the ceramic in between does not get out of the way (signed in blue line).
What am i doing wrong/ how would you do that operation?
Thanks
2024-11-27 03:29 PM - last edited 3 weeks ago by Laszlo Nagy
Hi @Zendrix,
IIUC, you can split this space at the yellow line illustrated below & create two slabs, one at the lower level as it is & one at the higher level with editing the slab composite to expand the cement filling layer to the structural slab top surface.