I have done a FARM terrain with the mesh tool with elevations variating from 890FT to 1100FT.
On a side I modeled the existing historical barn to be restored. (With the top of the slab @ 0'-0").
What is the correct thing to do, recess the whole mesh so the "spot" where the barn goes is 4" to 6" bellow my top of slab or should I rise the barn to the real elevation?
My concern in rising the barn is that I will have to work with this crazy numbers ( the top of slab instead of 0'-0" is going to be 935'-0").