Best practice for Hotlinks and multi-file Teamwork Project

cs_ryl
Booster

Hi All,

 

I'm trying to get some understanding of what the best practice is when it comes to a teamwork project that has multiple linked architectural models, and an overall site model, as well as consultant IFC models as hotlinks. 

 

We have come across issues when people working in the individual file who didn't update the relevant site/IFC hotlinks before working on it on a daily basic, which resulted in issues/clashes due to not seeing the latest from other models. 

 

What's the best practice to avoid this? Is it to always check the Hotlink Module Manager first thing in the day and hit the update button so that everyone working in the same model can pick up the latest? 

 

What about if there are changes through out the day which can be picked up through Send & Receive in the same file, but gets annoying when others have to always check and update the Hotlinks to pick up changes, etc. 

 

Any thoughts/previous experience/successful stories are welcomed! Thank you!

AC23 AUSTRALIA
MacBook Pro M1 2020 8GB Memory | macOS Monterey 12.3.1
6 REPLIES 6
ryejuan
Advisor

Usually it will all be stated in the B.E.P. but of course won't it be nice that if there are changes in each file and will prompt you to update. 

In the end what is your Objective?
ArchiCAD 9 onwards

Thanks for your reply @ryejuan. Yes agreed but also it can get really annoying if massive changes are happening in a short period of time - to avoid as best as possible of course. 

What do you mean by B.E.P? Can you elaborate on it? 

AC23 AUSTRALIA
MacBook Pro M1 2020 8GB Memory | macOS Monterey 12.3.1

BIM Execution Plan, it usually consist of a long list of things to do and not to do or how to handle your project that is using a BIM model and other processes that goes in your BIM file like how you're going to update the hotlinks of MEP IFC files etc. Other stake holders of that said project will have to agree and follow it. Thinking of a simpler way... you can treat it like a contract.

In the end what is your Objective?
ArchiCAD 9 onwards

that makes sense - thanks for that. I don't work as a BIM manager but gets involved in this part of projects quite often. Good to pick up the terminology 

AC23 AUSTRALIA
MacBook Pro M1 2020 8GB Memory | macOS Monterey 12.3.1
schagemann
Enthusiast

The best B.E.P. is useless if...

A. nobody reads it;

B. it is too complicated / extensive;

C. if your team is not Archicad proficient;

D. project architects do not manage / communicate efficiently;

 

Sounds to me that it might not necessarily be an Archicad related problem you are facing?

 

Are you using multiple AC files or is it a single file, also how big is the project team?

macinteract
Design Technology Managers.
All  on macOS | since AC 6

Archicad Framework > Smart Template 27
Smart Tree, Transmittal and Universal Label and other smart GDL Objects
By Architects for Architects.
ryejuan
Advisor

Yes, regardless of software, its more of the process how the whole team will execute it.

In the end what is your Objective?
ArchiCAD 9 onwards