I'm trying to create a wall schedule, but it doesn't want to list any "new" walls even though I didn't restrict the schedule with renovation status, layers or anything else. The schedule lists "existing" and "to-be-demolished" walls but not "new".
When I change "existing" walls to "new" - they don't appear in the schedule.
I don't know where to look anymore. Does anyone know the solution to this problem?
I have the last update of Archicad.
Archicad 25
Windows 11
Solved! Go to Solution.
2024-01-20 12:43 PM
Hi @Kresho,
That’s happening due to you are activating Existing renovation filter.
you can change to show all elements to be able to see all walls in schedule.
2024-01-20 12:43 PM
Hi @Kresho,
That’s happening due to you are activating Existing renovation filter.
you can change to show all elements to be able to see all walls in schedule.
2024-01-21 06:39 AM
Of course!
Thank you!
2024-01-21 02:56 PM
You’re welcome @Kresho