Ted wrote:Certainly how one handles tenant improvements may vary. But I wold have completed the base building first and added tenant improvements after. If the owner was also a tenant he would be charged for the base building and the improvements under one job. Subsequent tenants would be charged separately for each finish.
(gpowless) So (with ArchiCAD) would you then draw two separate tenant infills, occurring simultaneously in the same building, intwo separate models? And therefore never have one model that shows everything within the building? Or would you charge one client for drawing the information twice?