Calculated field in Zone Stamp

Anonymous
Not applicable
Hi

I'm trying to cook up a fancy zone stamp and as part of it I've calculated a field which shows successfully in the stamp in plan view. However, it isn't coming through to a schedule. Is there a way I can feed back my calculated value to the stamp so it will show in schedule?

TIA

Adri
1 REPLY 1
You have to have such parameter set up and via PARAMETER function You should fill this parameter up (preferably in parameter script or master script).

Best Regards,